Construction Financing

Dispensary Construction and Buildout Loans: Draws, Equity and Risk

Construction debt releases money in stages. Plan your equity, your draws and your license timeline together.

Updated October 202610 min readPillar Partners Editorial Team
Interior of a retail storefront under construction with exposed framing, work lights and a measuring tape on the floor
About this page: This is an informational overview built from public sources. Editors checked the cited sources. We have access to 75 lenders. Confirm details with the lender that best fits your situation.

The short answer

Construction loans fund a build in draws as work is done. Lenders usually want your equity in first.

SBA loans are off the table for most cannabis builds. Budget for interest and overruns before you apply.

Ground-up vs tenant improvement financing

TypeWhat it fundsMain risk
Ground-up constructionA new buildingCost, schedule and permits
Tenant improvementBuildout inside leased spaceLandlord consent and lease length
RenovationUpgrade of an existing siteHidden conditions

Tenant improvement lenders check the lease as closely as the budget.

How draws work

The draw cycleEquity in firstYour cashDraw requestWith invoicesInspectionWork verifiedFunds releasedTo you or vendorsRepeatUntil completeThe draw cycle
Money follows verified progress. Delays in inspections slow the build.

Ask how long a draw takes from request to funds. Slow draws hurt contractors.

Buildout Budget and Interest Carry

Estimate total project cost, loan, equity and interest during construction.

How to use this: Enter your budget and the lender's quoted loan-to-cost. The tool assumes draws arrive evenly, so the average balance is half the loan.

* Illustrative only. Not investment advice.

Why SBA is off the table

SBA programs do not serve most cannabis businesses. The agency's Form 1244 makes applicants certify no revenue comes from federally illegal activity.

Form 1244 names marijuana products and activities that support them.

Plan on private debt, owner equity or state programs instead.

Equity required before construction debt

Lenders usually want your equity in the project before they lend. One public lender targets collateral coverage of at least one times principal (10-K).

Ask what counts as equity, such as cash, land or paid costs.

Equity that is already spent may or may not count. Get the rule in writing.

Greenhouse and cultivation buildouts

  • Power and HVAC drive cost and permits.
  • Licensing inspections may gate occupancy.
  • Equipment may be financed separately.
  • Lenders check contractor experience.

See our equipment financing guide for gear that sits outside the construction loan.

Licensing contingencies

Construction can finish before a license is issued. That gap is a lender risk.

  • Write a license contingency into the contract.
  • Ask what happens if approval slips.
  • Check local hearing dates before you commit to a schedule.

A worked example: a $1.2 million buildout

These numbers are an illustration. They match the estimator above.

Hard costs are $1,200,000. Soft costs add 15 percent and contingency adds 10 percent. Project cost is $1,518,000.

At 65 percent loan-to-cost, the loan is $986,700. Equity required is $531,300.

Over nine months at 12 percent with even draws, interest carry is about $44,400. Total cost with interest is about $1,562,400.

ItemResult
Project cost$1,518,000
Loan$986,700
Equity$531,300
Interest carryAbout $44,400
Total with interestAbout $1,562,400

A sample draw schedule

This is an illustration of how a $986,700 loan might release in stages. It is not a lender schedule.

DrawMilestoneShareAmount
1Site work and framing25%$246,675
2Rough-in: electrical, HVAC, plumbing30%$296,010
3Finishes and fixtures30%$296,010
4Final inspection and occupancy15%$148,005

Ask each lender for its real schedule and its inspection timeline.

Mistakes to avoid

  • Underestimating soft costs and contingency.
  • Starting work before the license path is clear.
  • Ignoring draw timing in the contractor contract.
  • Assuming equity already spent will count.
  • Leaving overrun funding unspecified.

Ask the lender to show a sample draw schedule. It answers many questions at once.

Quick Check

See what capital you qualify for in under 3 minutes.

No origination fees for initial capital review. Terms depend on the deal and the lender.

Check Capital Eligibility →

Frequently Asked Questions

How the figures work: Figures with a link come from the filing or page named. Everything else is an illustration from the calculators, built on numbers you enter.

Sources and further reading

Ready to look at cannabis property financing?

Pillar Partners connects qualified operators with capital partners. No origination fees for initial submissions.

Affiliate disclosure: Pillar Partners may earn a referral fee when you use our partners. See our full disclosure policy.

Begin Capital Review →